SUPERVISION GERENCIAL DE DE LA EJECUCION DE 25 OBRAS DE SISTEMAS DE AGUA POTABLE 1 PUENTE VADO 3 ALCANTARILLADOS Y 35 OBRAS DE ELECTRIFICACION EN DIVERSAS LOCALIDADES Y MUNICIPIOS DEL ESTADO DE CHIHUAHUA.

CONTRACT SUMMARY PROII-CH-008-2015-PROII-CH-008-2015

Total amount

9.4 millones de pesos mexicanos (9,377,429.72 MXN)

Contract period(s)

Between 1 de mayo de 2015 and 31 de diciembre de 2015

This contract is part of a record. See record ocds-0ud2q6-PROII-CH-008-2015 in Open Contracting Data Standard format.

CONTRACT QUALITY

More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.

This contract has not been evaluated.

PLANNING

No data

CALL FOR TENDERS

Call type

LICITACION PUBLICA NACIONAL (open)

Call status

complete

AWARD AND CONTRACT

Call title

SUPERVISION GERENCIAL DE DE LA EJECUCION DE 25 OBRAS DE SISTEMAS DE AGUA POTABLE 1 PUENTE VADO 3 ALCANTARILLADOS Y 35 OBRAS DE ELECTRIFICACION EN DIVERSAS LOCALIDADES Y MUNICIPIOS DEL ESTADO DE CHIHUAHUA.

Award title

SUPERVISION GERENCIAL DE DE LA EJECUCION DE 25 OBRAS DE SISTEMAS DE AGUA POTABLE 1 PUENTE VADO 3 ALCANTARILLADOS Y 35 OBRAS DE ELECTRIFICACION EN DIVERSAS LOCALIDADES Y MUNICIPIOS DEL ESTADO DE CHIHUAHUA.

Contract title

SUPERVISION GERENCIAL DE DE LA EJECUCION DE 25 OBRAS DE SISTEMAS DE AGUA POTABLE 1 PUENTE VADO 3 ALCANTARILLADOS Y 35 OBRAS DE ELECTRIFICACION EN DIVERSAS LOCALIDADES Y MUNICIPIOS DEL ESTADO DE CHIHUAHUA.

Amount

9.4 millones de pesos mexicanos (9,377,429.72 MXN)

Signature date

30 de abril de 2015

Execution period

1 de mayo de 2015 to 31 de diciembre de 2015

Internal award code

PROII-CH-008-2015

This contract is (terminated)

IMPLEMENTATION