Total amount
4.3 millones de pesos mexicanos (4,304,579.75 MXN)
Contract period(s)
Between 24 de abril de 2018 and 22 de agosto de 2018Description
PAVIMENTACIÓN CON CONCRETO HIDRÁULICO DE AVENIDA INDEPENDENCIA TRAMO RIJO-TILAPA TRAMO 00+780.00 AL 1+560.00 EN LA LOCALIDAD DE TILAPA
This contract is part of a record. See record ocds-0ud2q6-LO-821176798-E4-2018 in Open Contracting Data Standard format.
More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.
This contract has not been evaluated.
MUNICIPIO DE TILAPA (Code: 821176798 )
Submission methods:
inPerson
Call period:
11 de abril de 2018 - 23 de abril de 2018
Call status
complete
Call title
PAVIMENTACION INDEPENDENCIA 00+780.00 AL 1+560.00
Award title
PAVIMENTACION INDEPENDENCIA 00+780.00 AL 1+560.00
Contract title
PAVIMENTACION INDEPENDENCIA 00+780.00 AL 1+560.00
Supplier(s)
Amount
4.3 millones de pesos mexicanos (4,304,579.75 MXN)
Signature date
24 de abril de 2018
Execution period
24 de abril de 2018 to 22 de agosto de 2018
Internal award code
1784356
No data
Date updated in QQW
11 de septiembre de 2019