Total amount
2.2 millones de pesos mexicanos (2,188,449.72 MXN)
Contract period(s)
Between 6 de agosto de 2013 and 16 de octubre de 2013This contract is part of a record. See record ocds-0ud2q6-IO-816006975-N3-2013 in Open Contracting Data Standard format.
More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.
This contract has not been evaluated.
Sec. de Obras Públicas, Desarrollo Urbano y Servicios Mun. (Code: 816006975 )
Invitación a Cuando Menos 3 Personas (limited)
Regulations: Z15122015 19. Invitación a cuando menos tres Nacional LOPSRM
Submission methods:
inPerson
Call period:
17 de julio de 2013 - 1 de agosto de 2013
Call status
complete
Call title
CONSTRUCCION DE LA CALLE FRANCISCO J. MUGICA Y ANTONIO MOCTEZUMA
Award title
CONSTRUCCION DE PAVIMENTO DE CONCRETO HIDRAULICO CON ADOQUIN Y GUARNICIONES EN LA CALLE FRANCISCO J. MUGICA Y ANTONIO MOCTEZUMA, COL. BENITO JUAREZ
Contract title
CONSTRUCCION DE PAVIMENTO DE CONCRETO HIDRAULICO CON ADOQUIN Y GUARNICIONES EN LA CALLE FRANCISCO J. MUGICA Y ANTONIO MOCTEZUMA, COL. BENITO JUAREZ
Supplier(s)
Amount
2.2 millones de pesos mexicanos (2,188,449.72 MXN)
Signature date
6 de agosto de 2013
Execution period
6 de agosto de 2013 to 16 de octubre de 2013
Internal award code
364042
No data
Date updated in QQW
24 de enero de 2019