Total amount
9.3 millones de pesos mexicanos (9,295,584.12 MXN)
Contract period(s)
Between 29 de agosto de 2013 and 31 de diciembre de 2013This contract is part of a record. See record ocds-0ud2q6-IO-009000997-N103-2013 in Open Contracting Data Standard format.
More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.
This contract has not been evaluated.
Centro SCT Hidalgo (Code: 009000997 )
Invitación a Cuando Menos 3 Personas (limited)
Regulations: Z15122015 19. Invitación a cuando menos tres Nacional LOPSRM
Submission methods:
inPerson
Call period:
20 de agosto de 2013 - 21 de agosto de 2013
Call status
complete
Call title
CONSTRUCCION DEL PUENTE PEATONAL KM 3+050 DEL DISTRIBUIDOR VIAL MUNICIPIOS UNIDO
Award title
CONSTRUCCION DE PUENTE PEATONAL MUNICIPIOS UNIDOS
Contract title
CONSTRUCCION DE PUENTE PEATONAL MUNICIPIOS UNIDOS
Supplier(s)
Amount
9.3 millones de pesos mexicanos (9,295,584.12 MXN)
Signature date
2 de septiembre de 2013
Execution period
29 de agosto de 2013 to 31 de diciembre de 2013
Internal award code
464848
No data
Date updated in QQW
24 de enero de 2019
Source(s)
Part of the project
Organization responsible for the import