Total amount
295,457.5 pesos mexicanos
Contract period(s)
Between 5 de agosto de 2013 and 18 de septiembre de 2013This contract is part of a record. See record ocds-0ud2q6-AO-018TOQ804-N96-2013 in Open Contracting Data Standard format.
More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.
This contract has not been evaluated.
Zona Tlaxcala (Code: 018TOQ804 )
Adjudicación Directa Federal (direct)
Regulations: Z15122015 22. Adjudicación Directa Nacional Art. 43 LOPSRM
Submission methods:
electronicSubmission
Call period:
19 de julio de 2013 - 26 de julio de 2013
Call status
complete
Call title
AO-018TOQ804-N96-2013 CONSTRUCCION OBRA CIVIL RED SUBTERRANEA
Award title
CONSTRUCCION DE OBRA CIVIL PARA SALIDAS SUBTERRANEAS DE LA SUBESTACION PAPALOTLA EN LA CALLE INDEPENDENCIA CORRESPONDIENTE AL AREA DE DISTRIBUCION TLAXCALA, DE LA ZONA DE DISTRIBUCION TLAXCALA, EN EL ESTADO DE TLAXCALA
Contract title
CONSTRUCCION DE OBRA CIVIL PARA SALIDAS SUBTERRANEAS DE LA SUBESTACION PAPALOTLA EN LA CALLE INDEPENDENCIA CORRESPONDIENTE AL AREA DE DISTRIBUCION TLAXCALA, DE LA ZONA DE DISTRIBUCION TLAXCALA, EN EL ESTADO DE TLAXCALA
Supplier(s)
Amount
295,457.5 pesos mexicanos
Execution period
5 de agosto de 2013 to 18 de septiembre de 2013
Internal award code
429151
No data
Date updated in QQW
24 de enero de 2019
Source(s)
Part of the project
Organization responsible for the import