CONSERVACION PERIODICA MEDIANTE RENIVELACION Y RIEGO DE SELLO DEL KM. 165 000 AL KM. 178 000 DEL TRAMO: JALPA - TABASCO DE LA CARRETERA: GUADALAJARA - ZACATECAS CON UNA LONGITUD DE 13.00 KMS EN EL ESTADO DE ZACATECAS.

CONTRACT SUMMARY 86CBA660W08-86CBA660W08

Total amount

7.1 millones de pesos mexicanos (7,077,392.04 MXN)

Contract period(s)

Between 1 de julio de 2008 and 28 de septiembre de 2008

This contract is part of a record. See record ocds-0ud2q6-86CBA660W08 in Open Contracting Data Standard format.

CONTRACT QUALITY

More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.

This contract has not been evaluated.

PLANNING

No data

CALL FOR TENDERS

Call type

LICITACION PUBLICA NACIONAL (open)

Call status

complete

AWARD AND CONTRACT

Call title

CONSERVACION PERIODICA MEDIANTE RENIVELACION Y RIEGO DE SELLO DEL KM. 165 000 AL KM. 178 000 DEL TRAMO: JALPA - TABASCO DE LA CARRETERA: GUADALAJARA - ZACATECAS CON UNA LONGITUD DE 13.00 KMS EN EL ESTADO DE ZACATECAS.

Award title

CONSERVACION PERIODICA MEDIANTE RENIVELACION Y RIEGO DE SELLO DEL KM. 165 000 AL KM. 178 000 DEL TRAMO: JALPA - TABASCO DE LA CARRETERA: GUADALAJARA - ZACATECAS CON UNA LONGITUD DE 13.00 KMS EN EL ESTADO DE ZACATECAS.

Contract title

CONSERVACION PERIODICA MEDIANTE RENIVELACION Y RIEGO DE SELLO DEL KM. 165 000 AL KM. 178 000 DEL TRAMO: JALPA - TABASCO DE LA CARRETERA: GUADALAJARA - ZACATECAS CON UNA LONGITUD DE 13.00 KMS EN EL ESTADO DE ZACATECAS.

Amount

7.1 millones de pesos mexicanos (7,077,392.04 MXN)

Signature date

25 de junio de 2008

Execution period

1 de julio de 2008 to 28 de septiembre de 2008

Internal award code

86CBA660W08

This contract is (terminated)

IMPLEMENTATION

No data

GENERAL INFORMATION

Date updated in QQW

9 de mayo de 2021

Part of the project

TodosLosContratos.mx

Organization responsible for the import

PODER