Construcciýn del Canal de Conducciýn y obra civil para interconexiýn de los pozos de la Planta Potabilizadora Mýrida IV. Segunda etapa.

CONTRACT SUMMARY 60105001-032-08-OP-JAPAY-036-2008

Total amount

2.6 millones de pesos mexicanos (2,580,328.43 MXN)

Contract period(s)

Between 7 de julio de 2010 and Fecha desconocida

Proveedor(es)

HOPNA, S.A. DE C.V.

This contract is part of a record.See record ocds-0ud2q6-60105001-032-08 in Open Contracting Data Standard format.

CONTRACT QUALITY

More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.

This contract has not been evaluated.

PLANNING

No data

CALL FOR TENDERS

Buying unit

Subdirección Técnica(Code: 60105001)

Call type

Licitación Pública(open)

Scope

Nacional

Purchase type

Obra Publica (works)

Call status

complete

AWARD AND CONTRACT

Call title

Construcciýn del Canal de Conducciýn y obra civil para interconexiýn de los pozos de la Planta Potabilizadora Mýrida IV. Segunda etapa.

Award title

Construcciýn del Canal de Conducciýn y obra civil para interconexiýn de los pozos de la Planta Potabilizadora Mýrida IV. Segunda etapa.

Contract title

Construcciýn del Canal de Conducciýn y obra civil para interconexiýn de los pozos de la Planta Potabilizadora Mýrida IV. Segunda etapa.

Supplier(s)

HOPNA, S.A. DE C.V.

Amount

2.6 millones de pesos mexicanos (2,580,328.43 MXN)

Signature date

7 de julio de 2010

Execution period

7 de julio de 2010 to Fecha desconocida

Internal award code

OP-JAPAY-036-2008

This contract is (terminated)

IMPLEMENTATION

No data

GENERAL INFORMATION

Date updated in QQW

9 de mayo de 2021

Source(s)

CompraNet 3.0

Part of the project

TodosLosContratos.mx

Organization responsible for the import

PODER