Total amount
45.9 millones de pesos mexicanos (45,941,902.71 MXN)
Contract period(s)
Between 5 de abril de 2010 and Fecha desconocidaThis contract is part of a record. See record ocds-0ud2q6-52010001-010-10 in Open Contracting Data Standard format.
More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.
This contract has not been evaluated.
Subsecretaría de Infraestructura (Code: 52010001 )
Call status
complete
Call title
Modernizaciýn y Ampliaciýn del Camino Rural E.C.F. (Muna - Felipe Carrillo Puerto) Km 180.5 - Dzoyola. Subtramo a construir Hobompich - Dzoyola del Km. 0+000 al Km. 18+576.468
Award title
Modernizaciýn y Ampliaciýn del Camino Rural E.C.F. (Muna - Felipe Carrillo Puerto) Km 180.5 - Dzoyola. Subtramo a construir Hobompich - Dzoyola del Km. 0+000 al Km. 18+576.468
Contract title
Modernizaciýn y Ampliaciýn del Camino Rural E.C.F. (Muna - Felipe Carrillo Puerto) Km 180.5 - Dzoyola. Subtramo a construir Hobompich - Dzoyola del Km. 0+000 al Km. 18+576.468
Supplier(s)
Amount
45.9 millones de pesos mexicanos (45,941,902.71 MXN)
Signature date
5 de abril de 2010
Execution period
5 de abril de 2010 to Fecha desconocida
Internal award code
CEE-OP-018/10
No data
Date updated in QQW
9 de mayo de 2021
Source(s)
Part of the project
Organization responsible for the import