DESARROLLO DE LA INGENIERýA BýSICA, INGENIERýA DE DETALLE, PROCURA DE EQUIPO Y MATERIALES, CONSTRUCCIýN, INTEGRACIýN CON LA REFINERýA, PRUEBAS, CAPACITACIýN, PREPARATIVOS DE ARRANQUE, ARRANQUE Y PRUEBAS DE COMPORTAMIENTO PARA LA PLANTA DESMINERALIZADORA DE AGUA DE 166 LPS DE AGUA DESMINERALIZADA "UDA-400", EN LA REFINERýA ING. HýCTOR R. LARA SOSA, EN CADEREYTA DE JIMýNEZ, N.L., MýXICO.

CONTRACT SUMMARY 18572039-002-08-ROPL03008P

Total amount

350.8 millones de pesos mexicanos (350,820,785.66 MXN)

Contract period(s)

Between 7 de mayo de 2010 and Fecha desconocida

This contract is part of a record. See record ocds-0ud2q6-18572039-002-08 in Open Contracting Data Standard format.

CONTRACT QUALITY

More than 20 algorithmic tests are run at the contract level, grouped into four categories, to determine the quality of procurement data. The methodology can be consulted here.

This contract has not been evaluated.

This contract has not been evaluated.

This contract has not been evaluated.

PLANNING

No data

CALL FOR TENDERS

Call type

Licitación Pública (open)

Scope

Internacional

Purchase type

Obra Publica (works)

Call status

complete

AWARD AND CONTRACT

Call title

DESARROLLO DE LA INGENIERýA BýSICA, INGENIERýA DE DETALLE, PROCURA DE EQUIPO Y MATERIALES, CONSTRUCCIýN, INTEGRACIýN CON LA REFINERýA, PRUEBAS, CAPACITACIýN, PREPARATIVOS DE ARRANQUE, ARRANQUE Y PRUEBAS DE COMPORTAMIENTO PARA LA PLANTA DESMINERALIZADORA DE AGUA DE 166 LPS DE AGUA DESMINERALIZADA "UDA-400", EN LA REFINERýA ING. HýCTOR R. LARA SOSA, EN CADEREYTA DE JIMýNEZ, N.L., MýXICO.

Award title

DESARROLLO DE LA INGENIERýA BýSICA, INGENIERýA DE DETALLE, PROCURA DE EQUIPO Y MATERIALES, CONSTRUCCIýN, INTEGRACIýN CON LA REFINERýA, PRUEBAS, CAPACITACIýN, PREPARATIVOS DE ARRANQUE, ARRANQUE Y PRUEBAS DE COMPORTAMIENTO PARA LA PLANTA DESMINERALIZADORA DE AGUA DE 166 LPS DE AGUA DESMINERALIZADA "UDA-400", EN LA REFINERýA ING. HýCTOR R. LARA SOSA, EN CADEREYTA DE JIMýNEZ, N.L., MýXICO.

Contract title

DESARROLLO DE LA INGENIERýA BýSICA, INGENIERýA DE DETALLE, PROCURA DE EQUIPO Y MATERIALES, CONSTRUCCIýN, INTEGRACIýN CON LA REFINERýA, PRUEBAS, CAPACITACIýN, PREPARATIVOS DE ARRANQUE, ARRANQUE Y PRUEBAS DE COMPORTAMIENTO PARA LA PLANTA DESMINERALIZADORA DE AGUA DE 166 LPS DE AGUA DESMINERALIZADA "UDA-400", EN LA REFINERýA ING. HýCTOR R. LARA SOSA, EN CADEREYTA DE JIMýNEZ, N.L., MýXICO.

Amount

350.8 millones de pesos mexicanos (350,820,785.66 MXN)

Signature date

7 de mayo de 2010

Execution period

7 de mayo de 2010 to Fecha desconocida

Internal award code

ROPL03008P

This contract is (terminated)

IMPLEMENTATION

No data

GENERAL INFORMATION

Date updated in QQW

9 de mayo de 2021

Source(s)

CompraNet 3.0

Part of the project

TodosLosContratos.mx

Organization responsible for the import

PODER